
Converting a Cornfield to a Sterile Field
BY MARK F. YEAGER, AIA
In our work across the U.S. as medical
specialty planners and architects, we solve difficult problems, including
complex program requirements, difficult site conditions, and compressed design
and construction schedules, for example. This article details one of our more
unusual cases.
Several years ago, I received a call from an ambulatory
surgery center (ASC) developer. He’d just been in a dispute with his design
team and had terminated their contract. He wanted me to accompany him on a
damage-control mission to visit a client located in a small Appalachian
community to brainstorm ways to move his project forward. He agreed to buy a few
hours of consulting time for ASC value-engineering that our firm is known for,
and I agreed to make the trip.
We arrived at a modest building that was a former police
barracks. The doctors had purchased it from the state and converted it to a
medical office and a physical therapy component. We were shown to the conference room where the doctors and
administrator were clearly upset because their expectations weren’t being met:
the project was behind schedule, the contractor bids were significantly over
budget, and the doctors were facing the probability of a delayed revenue stream
from the new facility. I thought, “This is about as bad as a situation can
get.”
But was I wrong. When I opened the construction documents, I
began to understand why the contractors’ numbers came in sky high. And the
longer I looked at the drawings, the more I realized that the project, as
designed, shouldn’t be built. The few hours of consulting with the doctors and developer
soon morphed into a total architectural and engineering redesign of the facility
— all on the developer’s dime. It was the only option that the developer and
the doctors had, short of throwing the whole mess to the lawyers.
The design called for a one-story, single-OR facility with a
walk-out basement for storage and mechanical space. Curiously, the basement walls were detailed as 18-inch-thick
concrete, chock full of steel reinforcement rods. It was the stoutest retaining
wall detail I have ever seen for a basement wall. I knew the area was neither
seismically active nor affected by unusually high-wind loads. Puzzled by the
missile-silo strength of the basement walls as detailed, I asked for the results
of the geotechnical report. I was informed one hadn’t been ordered.
Without an analysis of the soil-bearing qualities and a
recommendation for foundation design by a geotechnical engineer, there was no
basis for the design. The structural engineer tried to minimize his exposure to
liability by over-designing for resistance to lateral forces that may not be
present, in turn causing the contractor to waste the owner’s money on needless
materials and labor. Again I thought, “This is about as bad as a situation can
get.”
But I was wrong again. In the mountainous surroundings, the
site was extremely sloped. The doctors had purchased the site adjacent to their
medical office the year before, when it was still a corn field on the neighbor’s
farm. To keep the project moving along, the owner decided to construct the
septic tank and lateral field system for the future surgery facility on the rear
of the lot, leaving a tightly defined area in which to place the building.
The design for the driveway was for a 15 percent slope, steep
enough scrape the underside of a vehicle at the top of the ramp, and the bumpers
at the bottom. Parking spaces were on a 10 percent grade, making it a certainty
that a car’s passenger door, when unlatched on the downhill side, would fly
open, damaging the car parked next to it. Worse, the steepness created a slip
hazard for patients and staff.
We eliminated the basement, enabling us to lower the floor
level by several feet in order to make the driveway and parking grades work at a
reasonable slope. By eliminating the basement retaining walls and footings, and
utilizing a more economical slab-on-grade foundation system, we achieved a big
cost savings.
But we didn’t stop there. The floor plan in the original
design was organized like a miniature hospital instead of an outpatient
facility. By eliminating all the unnecessary circulation space, and with the
doctors’ enthusiastic approval, we converted the captured area to an extra
operating room and recovery space, and we created space for a few more chairs in
the waiting room to absorb the additional demand.
We decided to replace the basement storage area with a simple
expansion shell at one end of the building, creating a step in the foundation
where the two floors meet. This made the overall footprint larger and,
consequently, we had to use an architect’s shoehorn to make it fit among the
property boundaries, zoning setbacks, the septic field, storm water detention
areas, sidewalk and parking pavement, emergency power generator, condensing
unit, and the pump housing for the well that would supply the water to the
facility. It was tight but it worked, and we didn’t stop there.
For the exterior, the owner strongly preferred the plain look
of the existing medical office. We matched the brick, the siding, and the roof
pitch, and added a welcoming porte-cochere and a covered patient pick-up area.
The doctors and the developer enthusiastically approved the
new design. We had saved them money, created more efficient flow patterns with
additional productive space, improved the parking area, and added a covered
entry and patient pickup, making for a more user-friendly building. The state
department of health readily gave its approvals, and we released the
construction documents for a new round of bidding.
On the day the bids came in, everyone broke out in smiles. The
project had come in under budget and the owner was back on track. The project
was constructed that summer. Once the doctors moved in, obtained licensure and
certification, and started performing cases on a regular basis, the grievances
between the doctors and the developer were greatly diminished.
Planning and designing an ASC is not a cookie-cutter
operation; often problems surface that require the skilled response and
expertise of a seasoned design team.
Mark F. Yeager, AIA, is a principal of Design Consultants
International in Atlanta. DCI works exclusively with all medical specialties
nationally, achieving superior results in planning and design of ambulatory
surgery facilities and medical specialty offices.
Share this article: Email,
Slashdot, Digg,
Del.icio.us, Yahoo!MyWeb,
Windows Live Favorites,
Furl
Add this article feed to: RSS,
My Yahoo,
Newsgator,
Bloglines
|